Extra work being performed this week:

1) The completion of (2) 4″ conduits for Comcast and (2) 4″ conduits for Verizon. This will require about 18 lineal feet of trenching in the street on the West side of Hancock Street.

b) The installation of (1) 2″ conduit beginning at the same pole that the 4″ conduit stub is at, crossing Hancock, then across the county portion of the small island, across Highland and stopping at the pole on the East side of Highland.