Construction Schedule Through August 2010
May 27, 2010, 5:08 pm
Filed under: Construction Updates

The estimated project schedule calls for The Views at Clarendon to be completed by November 2011; below please find activities scheduled for June 2010 through August 2010.  Please note that this estimated project schedule includes only major work and is subject to change.

We will continue to provide updates similar to this throughout the construction process.

  • Install sheeting and shoring
  • Complete mass excavation of the building